Somersplash Waterpark — Lazy River (Largest in State) - commercial aquatic construction by Torwyn Solutions

Somersplash Waterpark — Lazy River (Largest in State)

Somerset, KY

Project Summary

Intense project from second week of April to end of May, working every day average 12 hours (some less, some upward of 15 hours). Just came off hard PCB job and this was even more intense with time crunch for opening day. Project discussed months in advance with architect in charge of building remodel scope. Over 1,100 linear feet and 15-16 feet wide with tons of wall jets, staircases, and two connected pools where big slide attractions fed in. Over 2,200 feet of coping combined. Deleted and patched old unnecessary tile line, ripped out old liner covering it, resurfaced cracked chipping loose floor material, redid long skimmer drain things on wall to be nice and square, addressed huge main drains in floor. Four people finished in that time frame with 200x better result than anything else, proving unmatched lazy river expertise.

Key Results

Project deliverables and measurable impact

26,000 sq ft of new membrane installed

1,030 linear ft river fully resurfaced

Completed in 45 days before season opening

Replaced severely failed membrane and unsafe concrete

Advanced work through Somerset–London tornado event

Initial Conditions

Challenges and issues identified at project start

  • Largest lazy river in the state needing remodel
  • Just finished hard PCB job
  • Tight opening day deadline
  • Over 1,100 linear feet and 15-16 feet wide
  • Tons of wall jets throughout
  • Multiple staircases
  • Two connected pools where slide attractions fed into river
  • Old unnecessary tile line present
  • Old liner covering pool
  • Cracked, chipping, and loose floor material
  • Long skimmer drain systems on walls in poor condition (crumbly concrete)
  • Huge main drains in floor

Work Performed

Detailed sequence of work completed

  1. Months of advance planning with architect
  2. Won bid for remodel
  3. Deleted and patched old tile line
  4. Ripped out old liner
  5. Resurfaced all cracked, chipping, and loose floor material
  6. Redid long wall skimmer drain systems to nice square shape
  7. Addressed huge floor main drains
  8. Installed over 2,200 feet of coping combined
  9. Worked every day for approximately 6 weeks
  10. Average 12-hour days, some 15+ hours
  11. Four-person crew completion

Outcomes & Results

Project deliverables and impact

  • Completed on time for opening day
  • Result 200x better than previous condition
  • Demonstrated unmatched lazy river expertise
  • Largest lazy river in state successfully remodeled

Professional Expertise Demonstrated

Contractor-level skills and certifications

  • Largest lazy river project in state
  • Intense deadline-driven project management
  • Architectural coordination and bidding process
  • Extreme work hours and dedication (12-15 hour days for 6 weeks)
  • Small crew high-output efficiency
  • Complex multi-feature waterpark integration
  • Over 2,200 linear feet of precision coping work

Stakeholder Coordination

Project collaboration and partnerships

  • Architect in charge of building remodel scope
  • Somersplash Waterpark management

Have a Similar Project?

Let's discuss how Torwyn Solutions can help with your commercial pool or waterpark project.

Request Consultation Resources

Looking for similar services?

Membrane Installation & Pool Construction →