The Residences at Zon Beachside — Rooftop Stainless Pool Design Problem Solving - commercial aquatic construction by Torwyn Solutions

The Residences at Zon Beachside — Rooftop Stainless Pool Design Problem Solving

Indian Harbour Beach, FL
October 2023

Project Summary

One week of labor over several months of plan revisions, finished October 2023. Stainless pool originally designed for tile finish until budget constraints. Contractor had multiple problems: pool built too low below outside floor decking that was supposed to meet pool edge, and needed code-compliant finish on stainless. After revising and resourcing correct materials, fixed height difference issue and waterproofed the pool. Worked during live construction of building being built and furnished. Welded custom logo into floor, lined large staircase, operated JLG Skytrak to move materials/tools/debris from 3rd floor roof. Solutions saved contractor from having to change beams at pool bottom to fix design issues, saving significant money.

Key Results

Project deliverables and measurable impact

Installed PVC membrane inside stainless-steel shell

Corrected coping and stair heights for code compliance

Welded custom logo panel into pool floor

All work hoisted to active 3rd-floor jobsite

Initial Conditions

Challenges and issues identified at project start

  • Stainless pool originally designed for tile finish
  • Budget could not cover tile on new luxury retirement complex/resort
  • Pool built too low below outside floor decking
  • Design issue where decking supposed to meet pool edge but couldn't
  • Needed code-compliant finish on stainless surface
  • Active construction site with building being built and furnished
  • Contractor facing expensive beam modification to fix design issues

Work Performed

Detailed sequence of work completed

  1. Months of plan revisions and material research
  2. Sourced correct materials to solve height and code issues
  3. Fixed height difference between pool and decking
  4. Waterproofed the stainless pool
  5. Worked in active construction environment
  6. Welded custom logo into floor
  7. Lined cool big staircase with membrane
  8. Operated large JLG Skytrak to move materials, tools and debris
  9. Coordinated logistics from 3rd floor roof
  10. Engineered solution to avoid beam modification

Outcomes & Results

Project deliverables and impact

  • Pool passed code without tile finish
  • Height difference issue resolved
  • Pool properly waterproofed
  • Contractor saved from expensive beam modifications
  • Contractor saved lot of money on design fix
  • Custom logo professionally integrated

Professional Expertise Demonstrated

Contractor-level skills and certifications

  • Complex design problem-solving for contractor
  • Material research and code compliance expertise
  • Rooftop construction and waterproofing
  • Heavy equipment operation (JLG Skytrak)
  • Multi-stakeholder coordination in active construction site
  • Structural engineering assessment (beam modification avoidance)
  • Custom welding and fabrication
  • Luxury resort-grade finishing work

Stakeholder Coordination

Project collaboration and partnerships

  • General contractor
  • Building construction teams during active build
  • Luxury apartment complex/resort management

Codes & Compliance

Building codes and regulatory standards

  • Code-compliant pool finish requirements

Have a Similar Project?

Let's discuss how Torwyn Solutions can help with your commercial pool or waterpark project.

Request Consultation Resources

Looking for similar services?

Membrane Installation & Pool Construction →